Quality records and a payment claim: where the two meet
A payment schedule that values your claim lower often gives quality as the reason. What an adjudicator can actually see, why the ITP and the NCR register belong in the claim rather than beside it, and what a bare assurance is worth.
The claim goes in for 214,000 dollars. The payment schedule comes back at 168,000, and the reason given is that part of the work is not to specification. Nothing in the claim says anything about specification, because quality lives in a different folder.
In Australia those are not two separate conversations, and treating them as two is expensive.
An adjudicator decides on what is in front of them
The security of payment regimes are built to be fast. The application and the response are made on documents, the timetable is short, and the decision is made on the material submitted. That has one blunt consequence: an assurance that the work was fine is worth very little, and a dated inspection record signed by two people is worth a lot.
The same is true one step earlier, at the payment schedule. A respondent who has to write down a reason for valuing the work lower writes a weaker reason when the claim already contains the records that answer it.
Which records actually answer a quality reason
- The approved ITP for that lot, showing which checks applied and who signed them off.
- The completed check records, with photographs where the criterion is visible and test sheets where it is not.
- The NCR register for the lot, including closed reports. A closed NCR with verified effectiveness answers the point better than the absence of any NCR at all.
- Hold point releases, because a released hold point is the other side agreeing at the time that the work was acceptable.
Why the closed NCR is the counter-intuitive one
The instinct is to keep NCRs out of anything that goes to the other side. It is the wrong instinct. A register with entries that were raised, dispositioned and verified shows a system operating. An empty register invites the reply that nothing was ever checked, and that reply is much harder to answer.
Attach, do not describe
There is a practical difference between a claim that says the work was inspected and a claim that carries the inspection record. The first invites a question, the second closes one. Where volume is a concern, a short schedule of the relevant records with the dates, and the records available on request, is better than a paragraph of assurance.
What the product does with it
VariationFlow keeps the quality records and the commercial records on the same project rather than in separate systems, so the records that answer a valuation reason can be produced for the lot and the period in question instead of being assembled from folders.
Decision support, not legal advice. What must be in a payment claim, and the times for schedules and applications, come from the Act in your state and from your subcontract.
One record, from the site to the payment