16 November 2026
Pay when paid clauses have no effect, in every state and territory
Every Australian Security of Payment Act strips a pay when paid clause of effect. What counts as one, where Victoria and Western Australia reach further, and why the Northern Territory words it differently.
The head contractor says the client has not paid them yet, so they cannot pay you. The subcontract even says so: payment to you within seven days of payment by the principal. It reads like a term you agreed to. Under every Australian Security of Payment Act, it does nothing.
What the Acts say
- New South Wales, s 12; Victoria, s 13; Queensland, s 74; South Australia, s 12; Tasmania, s 16; the ACT, s 14: a pay when paid provision has no effect in relation to any payment for construction work or related goods and services under the contract.
- Western Australia, s 14(2): the same, under the heading “Prohibited terms”. The WA note says these clauses are also called pay if paid or pass-through provisions.
- The Northern Territory, s 12: a provision has no effect if it makes a party’s liability to pay contingent, directly or indirectly, on that party being paid by someone else.
What counts as one
In the six East Coast Acts the definition has three limbs. A clause is caught if it makes the liability to pay you contingent on the payer being paid by a third party; if it makes your due date depend on the date the payer is paid; or if it otherwise makes the liability, or the due date, contingent or dependent on the operation of another contract.
The third limb is the one that matters in practice. A clause does not have to mention the principal by name to be caught. Tying your payment to the head contract’s certification cycle, or to the head contractor receiving a certificate, makes it dependent on the operation of another contract.
Where the definitions reach further
- Victoria (s 13(2), as amended in 2025) also catches a clause that makes your right to claim money, or your right to claim the release of a performance security, depend on another contract.
- Western Australia (s 14(1)) also catches a clause that makes the making of a claim, or the release of retention money or a performance bond, depend on another contract.
- The Northern Territory has no separate due-date limb in s 12, but s 13 reads any term requiring payment more than 30 working days after the claim as requiring payment within 30 working days.
What replaces the clause in Queensland
Queensland goes a step further. Under s 73(4), a contract that includes a pay when paid provision is treated as one that does not provide for when a progress payment is due, so the default applies: 10 business days after the payment claim is made.
You cannot sign it back in
The rights cannot be traded away either. In New South Wales, s 34 gives the Act effect despite any contrary contract term, and makes void any agreement that excludes, modifies or restricts it, or that may reasonably be construed as an attempt to deter a person from using it.
What to do with it
Claim as if the clause were not there. Serve the payment claim when the Act or the contract allows (on a reference date in Queensland, from the last day of the named month in New South Wales), endorsed where the Act requires it, and let the statutory clocks run from service. A reply that you will be paid when the head contractor is paid leans on a clause the Act has stripped of effect. Outside the Northern Territory, if no payment schedule arrives inside the window, the whole claimed amount falls due on the due date.
What the product does with it
VariationFlow counts the payment schedule window and the due date from the date the claim was served, in the business days of the state or territory the job is in. Nothing in it waits for the head contractor to be paid, because the Act does not either.